Advantages of a bill of quantities
A bill of quantities (sometimes referred to as 'BoQ' or 'BQ') is a document prepared by a cost consultant (often a quantity surveyor) that provides project-specific measured quantities of the items identified by drawings and specifications in the tender documentation for construction works.
A bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
At some stage in a project’s procurement process, regardless of the type of contract being used, the works will need to be quantified in order to obtain prices or to value the extent of the work and variations to issue payments. A good and accurate BoQ makes this process much easier and more transparent, and removes the reliance on guesswork. Before construction begins, the BoQ can inform the project budget and the modification of any elements of the design that may be prohibitively expensive. It can also help clarify quantities which means the correct materials can be procured in advance of the works starting.
A BoQ can provide a clear and extensive statement of the work that is to be completed, as well as a reliable base for budget control and accurate cost reporting. It enables the preparation of cash flow forecasts and provides a basis for the valuation of variations, the preparation of interim payments, and the final account.
For tenderers, it helps create a low-risk and low-cost tendering environment, which encourages the submission of competitive bids since the risk is better understood and defined.
[edit] Related articles on Designing Buildings
- Approximate bill of quantities.
- Bill.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- CESMM4.
- Common mistakes in bill of quantities.
- Cost plans.
- Elemental bill of quantities.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- Taking off.
- Tender.
- Types of bill of quantities.
Featured articles and news
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
College of West Anglia apprentice wins SkillELECTRIC gold.
Scottish government launch delivery plan
To strengthen planning and tackle the housing emergency.
How people react in ways which tend to restore their comfort.
Comfort is a crucial missing piece of the puzzle.
ECA launches Recharging Electrical Skills Charter in Wales
Best solutions for the industry and electrical skills in Wales.
New homebuilding skills hub launch and industry response
Working with CITB and NHBC to launch fast track training.